Lessons Learned

Dispute resolution for multi-contract projects: avoiding parallel proceedings and conflicting decisions

05/06/2019 15:11

Katie McDougallHector Sharp

Introduction

Construction contracts are commonly part of a wider suite of project contracts, involving multiple, overlapping parties. Depending on the project, this suite can include concession and licence agreements, joint venture agreements, offtake agreements, financing agreements, direct agreements, guarantees and agreements with subcontractors. This intertwined suite of contracts often means that when a dispute arises, it arises under multiple project contracts. Each of those contracts may have a well-drafted dispute resolution clause that was negotiated and agreed by the specific parties to that contract, and which reflects how those parties wish to resolve any dispute under that particular contract. However, such clauses often differ and are incompatible.

This disparity in dispute resolution procedures across multi-contract projects can lead to a series of concurrent arbitrations and court proceedings relating to the same or similar issues arising in connection to the project, potentially resulting in conflicting decisions. The costs and time burden of dealing with multiple disputes on multiple fronts can be significant, and the difficulties of enforcing conflicting decisions will inevitably delay the satisfactory resolution of such disputes.

In some circumstances, this is the commercial reality of such projects and may not be a priority for different parties. However, if mitigating these risks is a priority, such mitigation may be achieved through arbitration and the consolidation of arbitral proceedings. Although difficult to accomplish, steps can be taken to give parties the best chance of achieving consolidation, and therefore avoid some of the issues associated with multi-contract projects. This article answers some FAQs regarding these issues.

FAQs

What are the key issues faced in drafting dispute resolution clauses for multi-party and multi-contract projects?
Large projects will inevitably have many moving parts – multiple parties in different jurisdictions, financiers, sponsors and contractors and large volumes of interlinking contracts. The contracts will often be drafted across different internal and external legal teams, including situations where multiple firms are advising on contractual terms. Various parties to these contracts, especially government entities and lenders, will push for particular dispute resolution procedures, based on their internal policies or commercial drivers. Other parties may have differing experience with dispute resolution procedures, or particular arbitral bodies or seats of arbitration, which lead them to prefer a particular procedure. This inconsistency can cause issues when a dispute arises under multiple contracts, including concurrent proceedings and conflicting decisions.

What is the key to mitigating these risks?
Consistency across dispute resolution clauses is key. This could be achieved by choosing the courts of a particular location to have exclusive jurisdiction over disputes arising under any project document. However, if the project has several parties from different jurisdictions, this may not be commercially palatable.

Choosing arbitration as the dispute resolution procedure for each project contract – and ensuring that the arbitration agreement in each project contract is consistent – will likely be a more palatable option and will give the parties a good chance of achieving consolidation of future disputes under different project contracts. Including specific drafting relating to consolidation will also be helpful.

What is meant by 'consolidation' and how is it different to 'joinder'?
'Consolidation' is where two or more separate arbitral proceedings are merged into a single arbitration. The merged arbitration can be presided over by one of the existing arbitral tribunals or a new arbitral tribunal can be appointed for the merged arbitration. The two separate arbitral proceedings can relate to disputes under the same contract or under different contracts but arising from similar facts. However, for the purposes of this article, the focus is on situations where disputes arise under different project contracts but in relation to the same facts.

'Joinder' is where, on the request of an existing party to an arbitration, a third person not yet involved in the arbitration is brought in to participate in the proceedings, or where the third party is allowed to intervene in an existing proceeding.

What are the recommended initial steps?
If possible, a holistic review of the proposed dispute resolution procedures for all project contracts should be taken. The proposed dispute resolution clauses should be compared to see if consistency is possible and negotiations should be conducted with this in mind. If a project contract has already been executed, the parties to the other project contracts should consider whether the dispute resolution procedure adopted by the executed contract can be mirrored in the remaining contracts. If not, an amendment to the signed contract can be considered.

Further, an analysis of where disputes are likely to arise should be conducted. If total consistency cannot be achieved across all project contracts, it may still be helpful to achieve consistency across a set of contracts under which similar disputes may arise.

What role does arbitration play?
For many different reasons, it is common to see arbitration as the preferred dispute resolution procedure in multi-party project contracts, especially for those projects that involve international parties. Arbitration is often seen as a more neutral forum than a local court alternative, and in many circumstances can be beneficial for enforcement. Many of the most commonly used rules of arbitral institution, including the International Chamber of Commerce and the London Court of International Arbitration, have provisions dealing with joinder and consolidation, and give the court of the respective arbitral institution the discretion to make appropriate orders in certain circumstances. Such rules differ in their content, but the key to taking advantage of them, particularly in respect of consolidation, is to ensure that the essential parts of the arbitration agreement in each project contract are consistent. These essential parts will include the seat of arbitration, the arbitral rules and the number of arbitrators. However, they may also include any specific procedural requirements written into the arbitration agreement.

What effect does differing governing laws between contracts have?
Parties often believe that consolidation cannot be achieved where proceedings are brought under different contracts providing for different governing laws. However, while it may affect a tribunal's discretion in deciding whether to consolidate, it is not necessarily the case that different governing laws in all cases will prevent consolidation. Arbitral tribunals regularly determine points of law under different legal systems, and this would be no different in a consolidated arbitration. Accordingly, if, say, it was necessary to determine whether a particular fact scenario gave rise to a breach of an engineering, procurement and construction contract governed by New York law, and then also whether that same factual scenario gave rise to a breach of a concession agreement governed by English law, the arbitral tribunal in a consolidated arbitration can make such determinations.

What effect do stepped or split clauses have on consolidation?
Split clauses – clauses which provide that at the point when the dispute arises one or more parties has the option to choose the dispute resolution mechanism (whether court or arbitration) – can mean that consistency across project documents, and therefore the ability to consolidate disputes, is lost.

Similarly, stepped clauses, which provide that several dispute resolution processes must be gone through before proceedings can be commenced (eg, first negotiation, then mediation and then finally arbitration), can also mean that consolidation is not possible.

The perceived advantage of such clauses may outweigh the desire to achieve consolidation. However, this is something that should be considered by the parties upfront.

Should a consolidation clause be included and what should it contain?
While notoriously difficult to draft, thought should be given to including a consolidation clause within the dispute resolution clause of each project contract, which expressly evidences the parties' agreement to consolidation. The specific drafting of such clauses will depend on the arbitral rules chosen (as there may be different requirements relating to agreements to consolidate), and also the contracts to which the agreement to consolidate will apply. Again, consistency of such consolidation clauses across project contracts is key.

For original upload, click here. 

Share Post
SOME OTHER NEWS
  • The UK Supreme Court to Hear Deepwater Horizon Appeal Seeking Removal of an Arbitrator 05/06/2019 14:53

    The UK Supreme Court will hear an appeal from Halliburton Company v Chubb Bermuda Insurance Ltd [2018] EWCA Civ 817 on whether an arbitrator may accept appointments in multiple references concerning the overlapping subject matter with only one common party, without giving rise to an appearance of bias and without disclosure. As it stands, the decision of the Court of Appeal means that arbitrators can accept multiple appointments in arbitrations with overlapping subject matters, without disclosure, and without necessarily giving rise to doubts about their impartiality.

  • Confidentiality of Already Disclosed Documents: Admissibility of Improperly Obtained Privileged Evidence 27/05/2019 16:23

    Arbitral tribunals have, in various instances, allowed parties to rely on documents obtained illegally as evidence. Practically, however, such documents are of a privileged character, e.g. emails exchanged between attorneys and clients, any information related to a set of confidential proceedings or communications between a psychotherapist and a patient. Privileged documents deserve higher legal protection and they cannot be admitted as evidence in arbitration proceedings. 

  • International arbitration 23/05/2019 10:31

    Arbitration offers a compelling forum for resolving international commercial disputes. As a consequence, there is now greater competition between traditional arbitral seats and emerging institutions – rivalry that is leading to greater efficiencies and innovative services. In an ever-changing socioeconomic world, issues such as increasing transparency requirements and transformative technological advances will do much to shape and define the international arbitration community over the coming months and years.

  • Court upholds jurisdiction of tribunal over settlement agreement lacking express arbitration clause 07/05/2019 09:51

    In Sonact Group Limited v Premuda SPA, the High Court found that a tribunal had jurisdiction over a dispute that arose from a settlement agreement lacking an express arbitration clause. Mr Justice Males held that the parties had intended that the arbitration clause contained in the underlying charterparty would continue to apply to the informal settlement agreement. The court took into account industry practice and found that it would be extraordinary if the parties had not intended to remain bound by the arbitration clause.

  • Are recordings made without consent of counterparty admissible as evidence in arbitration? 11/04/2019 10:24

    In a recent arbitration, the claimant and the respondent were both large state-owned mining enterprises which had entered into a long-term iron ore transaction. Each year, the parties had signed a sales and purchase agreement, which had set out the manner in which the claimant would sell iron ore to the respondent.

  • Need for speed: get your anti-suit injunction fast! 11/04/2019 10:11

    Parties entering into arbitration agreements ordinarily abide by their contractually chosen dispute resolution mechanism and proceed accordingly. However, counterparties sometimes start proceedings in a foreign jurisdiction in breach of an arbitration clause. How does an innocent party restrain such conduct?

  • Art and Arbitration: What Needs To Be Done To Improve The Security Of Art Sales And Transactions 29/03/2019 11:24

    What can be done to increase the trustworthiness of this opaque yet dynamic market?

  • Summaries and Issues in the ICC Terms of Reference: The Right Level of Case Management 26/02/2019 09:48

    What are Terms of Reference in the ICC Rules of Arbitration, and what are they for?

    REGISTER EMAIL WITH VIAC